Close×

An enhanced support regime and improved teamwork are allowing the RAN’s 14-strong fleet of Armidale-class patrol boats to again meet designated availability requirements notwithstanding a punishing operational tempo and continuing problems with cracking of their aluminium hulls and superstructures.

The challenges arising from both issues are readily acknowledged both by the Chief of Navy, Vice Admiral Ray Griggs, and by Greg Hodge, CEO of DMS Maritime, which holds a 15-year support contract for each boat, the first of which was commissioned in 2005 and the last, HMAS Glenelg, in 2008.

But for both men the worth and viability of the Armidales remain unquestioned, although VADM Griggs believes their life of type may be closer to 15 than to 20 years should the current work rate continue.

Seven of the Armidales are allocated at any one time to Border Protection Command (BPC) and Operation Resolute – the protection of Australia’s borders and offshore maritime interests over an area constituting about 10 per cent of the earth’s surface.

The rotation

This tasking takes place on a rotational basis, so all 14 boats contribute to Resolute which, according to VADM Griggs, accounts for 80 per cent of the 3,500 annual sea day availability contracted for the Armidales by DMS. An additional 600 days of “surge” availability is also contracted but would involve tradeoffs in maintenance, he added.

The rotation also means that the entire fleet shares in facing what VADM Griggs describes as the difficult environment encountered in the northern and northwestern approaches.

“They’re not operating outside of their design environment and that’s a bit of hysteria that has been overplayed, but they’re certainly operating at the top end of what we’ve intended,” he comments. “One of the big things you can’t avoid when you’re coming around from Christmas Island is that for six or seven months of the year up north you’re bashing into the southeasterly trades to get home and that’s going to have an impact.”

Some cracking of the Armidales’ conventional welded aluminium alloy structure had been anticipated, since this was the RAN’s first major foray into aluminium construction of a vessel that would experience serious weather and operate at speed, the VADM said.

Repairs

Although first-of-class HMAS Armidale had been temporarily restricted to training duties after cracking had been discovered in the engine room area, this had not affected the number of boats available for Resolute. This was also true of the hull corrosion which obliged HMAS Bathurst to undertake repairs in Singapore last August.

Such repairs could be as simple as welding the crack, others might require more complex reinforcement work, but all involved approval by the Det Norske Veritas certification agency, Hodge said.

Meanwhile a hull and structure working group was employing advanced modelling to analyse stress and identify areas that would benefit from strengthening in advance of any cracking. Two Armidales that had been fully instrumented by DSTO were providing a mass of information linked to the ship control system on G forces and other issues, VADM Griggs disclosed.

“Now we can say, you had a sea state of this, the waves were 40 deg on the bow, you were doing 20 knots. That’s been really useful; to start educating our ship COs who, frankly, have all grown up driving steel boats. Steel cracks too, but in a different way.”

A capability review initiated after a two-day trip in Armidales to Ashmore Island in late 2011 had reinforced the need for positive action to fix systemic issues in sustainment and maintenance, including mythology surrounding the support contract on who did what. This resulted in a decision to transfer an extra 330 operational availability days to maintenance in 2012, a year which saw some 290 SIEV (Suspected Illegal Entry Vessels).

“You couldn’t have had a more challenging operational year to put maintenance before operations but we did it. Our availability went from 3,500 days down to 3,100 on an annualised basis until 1 January, then we went back up to 3,400 and we’ll stay there until July or August, when we’ll be back at 3,500,” VADM Griggs said.

This was primarily to catch up on a backlog of maintenance flowing from the last two Armidales being upgraded in 2011 to the Glenelg product baseline in a so-called Post Availability Maintenance (PAM), a period during which DMS continued to provide annualised availability of 3,500 days through greater demands on the 12 other vessels.

As pointed out by Harley Tacey, DMS Maritime’s Chief Operating Officer, the amount of work that can be completed within the normal cycle of two week maintenance/six week operations is limited.

Last year’s temporary move to three weeks maintenance/five weeks operations disposed of the backlog and the 2x6 cycle should be fully reinstated by September by when DMS Maritime will have completed modifications to the Armidales’ stern tubes (through which the propeller shafts are carried), Tacey said. According to the Australian National Audit Office’s 2011-2012 Major Projects Report, design failures in the stern tube bearings have severely impacted vessel availability.

The problem, as detailed by Hodge, was a mixture of corrosion in the tubes and excessive marine growth. Turning the shafts can break the growth, dislodge it and block the cooling galleries, leading to premature degeneration of the bearing.

Changes to the bearing material and improving the original design of the seal will take the man out of the loop for day-to-day maintenance of the tubes and reduce the need for the shafts to be turned.

Post-Rizzo

The post-Rizzo period has seen the emergency of what is clearly a significantly more cohesive support structure. A widespread perception that there was no room for Navy in maintenance activities has been laid to rest with eight members of the Fleet Support Unit (FSU) embedded in DMS Maritime’s Armidale support team.

“We’re getting extra skills in a labour-strapped environment and Navy are getting exposure to additional on-the-job technical experience. It’s a win/win arrangement,” Hodge explained to ADM. “In Darwin and Cairns we’re fishing in a small pool for appropriately-qualified people and getting access to trained people in the FSU has been beneficial to all.

“We’ve had to repatriate some of the ILS (Integrated Logistics Support) engineering tasks back to Sydney because there simply aren’t people in Darwin to staff the degree-qualified positions.”

However, the most significant step in bolstering leadership and practical cooperation occurred in mid-2012 with the creation at VADM Griggs’ suggestion of Team Armidale.

“It’s taking the enterprise approach to the situation in the way in which ASC, DMO and Navy are communicating in Team Submarine,” he commented. “It doesn’t cut across any contractual things; it’s really an extension of the partnership approach. My idea was to get DMO, DMS and Navy leadership much more tightly orchestrated.

“On my trip to Ashmore Island I asked questions about really basic support issues and I got wildly different answers about who could do what. What I was keen to do was debunk mythology about the support contract and create a joint leadership team, and that has worked very well.

“Tim Barrett (Fleet Commander), Peter Marshall (then-head of Maritime Systems at DMO) and Greg Hodge talked to the COs of the boats, to the more senior people with the DMO Systems Program Office (SPO), to DMS Maritime, and also to the senior technical people in the boat and ashore – the people who have got to make it work on a day-to-day basis.”

Two meetings last year involved all available DMO, DMS, SPO and Navy people in one room, Hodge said.

“We went through a number of presentations to each other so that people gained an appreciation of the issues we all face and it was a real opening up of communications. We’re having another in June, it’s breaking down stovepipes, it’s going beyond the contract, it’s a partnership and it’s great.”

VADM Griggs also identified the emergence of a much stronger focus on obsolescence management and identifying the root cause of defects, a path being pursued by a separate lower-level Team Armidale group looking at a remediation plan that will incorporate all the issues affecting Armidale operability and maintainability.

The limited maintenance capacity available at Darwin and Cairns - the latter also the support base for the RAN’s hydrographic assets – has been a long-term cause for concern. New ground is now being broken with Aluminium Boats in Brisbane undertaking its first Armidale maintenance period.

Morale
VADM Griggs describes crew morale as “far more robust than people give it credit for”, helped in particular by the government’s decision to award an operational service medal for border protection. This was a boost for the many crew members who chose to spend the majority of their careers in the patrol boat fleet.

Multi-crewing involves 21 crews, each 23-strong, rotating through the 14 boats on a watch cycle of eight weeks on, four weeks off.  For some time the model has involved three crews across two boats, providing the crews with a sense of ownership.

“When you’re swapping crews between the ships you know you’re giving it to someone you’re going to get it back from, so that makes the three crews start thinking more as one,” VADM Griggs commented.

DMS Maritime’s contracted 15 years of Armidale support has a five year option, and Hodge says the company has recently initiated a number of engineering assessments to ensure the boats deliver 20 plus years of service.

VADM Griggs sees no reason why the fleet could not get through to 20 years, but questions where the three-phase bathtub curve (early reliability failures, random failures, wearout failures) will kick in.

“We were always planning at having seven boats in border protection, but whether it was fisheries (protection) or people smuggling, that obviously changes the profile a little bit. If they continue to work really hard, I think it will probably be closer to 15 years than to 20.” 

comments powered by Disqus