Projects: AWD and LHD coming together | ADM December 2012/January 2013
By Julian Kerr | Sydney | 15 February 2013
In
bustling facilities some 650km apart, the eventual shapes of the RAN ’s first
Hobart class air warfare destroyer (AWD) and its first Canberra class Landing
Helicopter Dock (LHD) are becoming increasingly recognisable.
In practical terms, the physical evidence of the advances being
made by ASC and the AWD Alliance at Osborne near Adelaide and by BAE Systems
Australia with the LHD at Williamstown in suburban Melbourne not only
demonstrates the magnitude of each program but also provides a handy reference
point by which future progress can be measured.
The AWD schedule has now been rebaselined twice in 18 months;
first in May 2011 when completion of the first of the threeship class was
delayed by a year until December 2015, and again this September when delivery
was pushed back another four months to March 2016 and the keelto-keel interval
between ships was extended from 12 to 18 months. Ship Two will now follow in
September 2017 and Ship Three in March 2019.
While the first delay was caused the need to reallocate the
construction of ship blocks due to a production bottleneck, the second is
intended to both help avoid a decline in naval shipbuilding skills prior to
work beginning on the Future Submarine, and to reduce Navy’s challenge in
introducing the AWD and LHD at much the same time.
The delayed expenditure of $100 million will also assist in
achieving the government’s objective of a budget surplus, a point acknowledged
by Defence Minister Stephen Smith. That said, industry has also been generally
welcoming of the schedule change both in terms of reducing project risk, and
retaining skilled personnel.
Notwithstanding these adjustments, Andrew Cawley, General
Manager Programs at the Defence Materiel Organisation (DMO), says the schedule
remains challenging – “not ridiculous otherwise it’s ignored, and not so slack
that no one cares.
“We’re keeping the pace on and Ship One is genuinely a very busy
work in progress; we’re going through the whole rebaselining down to detail
that includes something like 40,000 activities. The year’s extension doesn’t
apply to every worksite and every category of the workforce but it does apply to
important parts of it.”
The keel-laying ceremony on 6 September involved two of the 30
pre-outfitted blocks (plus a separate composite sonar dome) that will make up
each AWD. Three months later, a further four keel blocks had been or were in
the process of being consolidated, and two accommodation blocks had been placed
on top of the two original keel structures.
As of late November, all seven blocks being constructed by BAE
Systems for Ship One had arrived at Osborne as had seven of the 14 Ship One
blocks being made by Forgacs at Tomago and Carrington near Newcastle. ASC is
constructing the other nine blocks at Osborne, and the sonar blocks for both
Ship One and Ship Two will be delivered by Navantia next July.
Virtually the entire hull and superstructure should be completed
by late next year, after which internal work will continue on long cable runs
and setting systems to work.
Equipment
As construction proceeds, so does the delivery of equipment.
Warehouses are filled with materiel ranging from galley units through to 5inch
gun mounts, SPY 1D(V) phased array radar faces, Mk 41 missile vertical launch
systems, GE LM 2500 gas turbines, diesel engines, and AN/SPQ-9B horizon-search
radars.
Although the main reduction gearboxes have been received ready
to be installed as the relevant hull sections are consolidated, the drive
shafts and propellers have yet to arrive from Spain, as is much of the AEGIS
combat system Capability Baseline 08 software.
“Some changes have to be made to the AEGIS software to cater for
the fact that our ship is different to an American Arleigh Burke (missile
destroyer) or an American Ticonderoga (cruiser),” Cawley explained to ADM.
“We have a different number of missile cells, the missile
directors are in different places, this is basic data about the configuration of
the ship. Otherwise we’re making so few changes to the core system that it’s
more of a maintenance update than a major redevelopment.”
This situation has been facilitated by the Kongsberg-developed
Australian Tactical Interface (ATI) architecture that provides an interface
between AEGIS and Australian-specific subsystems such as the sonar and
electronic warfare suites, VAMPIR infrared search and track, the electro-optic
system, torpedo tubes, and close-in defence weapons.
Progressive testing of these and other subsystems has been
underway both at vendors’ facilities, and at the land-based test site (LBTS)
established by Raytheon Australia at Macquarie Park in Sydney.
A recent test validated the ability of the Babcock
Australia-manufactured Mk32 Mod 9 torpedo launcher destined for the AWDs to
fire a MU90 lightweight torpedo. The Mod 9 is an unusual “under and over” two-barrel
led variant of the US triplebarrelled Mk32 launchers now equipping the RAN’s
Anzacs and FFGs.
Uniquely, instead of being installed on deck, Mod 9 launcher
assemblies will be installed port and starboard in the aft section of each AWD,
discharging their torpedoes through a hatch in the side of the ship.
Cawley also reports worthwhile progress in development of the
Ultra Electronics’ AWD sonar suite after Raytheon Australia as the combat system
systems engineer put significant effort into ensuring the work was well-defined
and well-structured.
“It was more a reorganisation to ensure the equipment that was
needed in the shipyard got priority and software was ready when required. The
system integrates a fairly mature hull-mounted sonar and a towed array; we’re
developing some of the algorithms to improve performance but it hasn’t been
installed on an F-100 design, so not everything to be done is just software,”
Cawley notes.
“The large winch for the towed array has to be installed in the
stern block in a way that fits and allows safe operation. That and the cabinets
that have to be down there close to where the array comes into the ship all had
to be designed by Navantia and Ultra, and that took quite a lot of time.”
As construction proceeds, the 2,500-strong AWD workforce at
Osborne, Williamstown, Tomago and Carrington will be boosted from time to time
by integration experts from Spain and the US.
One crucial task for specialists from ASC, Navantia and Bath
Iron Works will be aligning each of the two gas turbines and diesel propulsion
engines aboard each ship with a reduction gearbox, then aligning that with a
drive shaft, stern gland and propeller.
“One engine room runs short to the stern and the other in front
of it runs longer by the length of that machinery room, meaning one shaft is a
lot longer than the other,” Cawley said. “It’s fairly standard but it doesn’t
make it a simple task.
“The power in these systems means you must have very precise
alignment and balance otherwise you can easily get vibrations which affect the
radiated noise of the ship and can affect your ability to get full power. You
should try and use the same team to do all three ships which is one of the
benefits of slipping the schedule; this means one team can set the one ship to work
then move to the next ship, and then the next one.”
Timeline
What is not generally appreciated is that the date of an AWD’s
delivery is not when it first leaves the ASC facility, but when it is
eventually handed over by the DMO to the RAN for the navy’s own operational test
and evaluation activities.
The hull is generally launched about 12 months prior to delivery
– in the case of the future HMAS Hobart, sometime in early 2015. Six to seven months of final set to
work is carried out at dockside on main machinery, and the combat system receives
its final alignment. Several months of DMO sea trials are then followed by
final remediation, preparation, signoff and handover to the RAN.
LHD
The hull of LHD01 arrived in Port Phillip Bay on 17 October
aboard the heavy lift ship Blue
Marlin, with more than 700 tonnes of welded steel
girders dedicated to keeping the 230 metre long structure stable during its
nine-week voyage from Spain. The girders then had to be cut away and the ship
floated off and towed to Williamstown, arriving nine days later.
Ventilation, lighting and alarm systems were activated over
several days after which the first of the four blocks making up the
superstructure – all of broadly similar dimensions and weighing between 250 and
300 tonnes – was lifted onto the hull, and welded into place in a 24-hour long
exercise.
Prior to that, measurements of the flight deck and the
underlying strength structure had been established to within 10mm to enable “the
green “ – steel beyond the anticipated dimensions (normal ship building practice)
– to be cut from the block before it was moved to the hull.
Installation was dependent on calm conditions to avoid ship
movement, all four blocks were in place well before Christmas.
Given that sea trials are currently set for late 2013 (and
delivery for early 2014), weather-induced or any other delays represent risk to
a tight schedule. This applies equally to Ship Two, which barring unforeseen
circumstances will arrive in Australia in the first quarter of 2014 and be
handed over to the RAN in August 2015. On completion of superstructure
consolidation on LHD01, attention will turn to connecting power, ventilation
and fluids to the superstructure followed by the installation, integration and
testing of electronic systems.
“The main hull has been fully outfitted so it’s got all the,
pods, diesel generators, transformers, machinery control systems, fire mains,
sea water, fresh water, and a lot of that has been tested and set to work,” Cawley
told ADM.
“There are some tests to be completed, there’s some minor work
to be completed, and we have to inspect more than 1,000 compartments prior to
the Commonwealth accepting the ship, and that is not a trivial exercise”.
The 9LV Mk3E combat management system (CMS) produced by Saab
Systems for the Anti-Ship Missile Defence (ASMD) project for the RAN’s Anzac
class frigates is also destined for the LHDs. This is a new generation, open
architecture system that is both modular and scalable, allowing for a variety
of configurations.
Aboard the LHDs, the CMS must not only bring all the ship’s
sensors, communications and weapon into a single, highly-integrated entity, but
must also handle the additional complexities involved in watercraft and
helicopter operations.
According to Cawley, development is still underway at the
Williamstown LBTS and the requirements for final certification will include a
satisfactory 48-hour stability test.
While considerable derisking can be achieved at the LBTS, such a
facility is not able to simulate all the dynamics of the ship or the isolation
from surrounding electro-magnetic influences. This means testing of the CMS and
the primary surveillance radar must take place aboard after completion of the
superstructure construction and fitout.
Unusually for such large and important combat assets, the LHDs’
self-defence capability will be limited to four Typhoon 25mm remote weapon
systems, one on each corner of the flight deck. The Nulka active missile decoy
system will be fitted on the LHDs soon after delivery to the RAN, Defence has
confirmed.