The Government’s development works at Gallipoli Barracks, Enoggera, are well over the halfway point, with
$573 million of the total expected cost of $788 million having been spent. Over
$149 million has already been spent this financial year.
The works are part of the Enhanced Land Force project, which will
see the modernisation and increased capacity of Defence facilities across the
country.
Parliamentary Secretary for Defence Senator David Feeney inspected the works.
“This Enhanced Land Force project is a priority for the Government
and demonstrates a clear long term commitment to Gallipoli Barracks and the
Defence community living here,” Senator Feeney said.
“These works will provide the Australian Defence Force at Enoggera
with modern, purpose-built facilities. These new facilities allow for the
effective operational and training requirements of 7th Brigade, which has
expanded under the Enhanced Land Force initiative.
“You will definitely start seeing more facilities in the coming
months, as we see the completion of car parks, 7 Combat Support Regiment
facilities, the Defence Clothing Store and the Defence Publishing Centre. In
fact, the new $80 million facilities for 8/9 Battalion RAR (Royal Australian
Regiment) were officially opened by the Chief of Army on 27 March.
Senator Feeney explained that the works commenced in June 2010 and
are expected to be completed by the end of 2014. On average, these works have
delivered over 500 jobs that would not have existed otherwise.
“These modern facilities also mean increased effectiveness and
efficiency for Defence personnel working and training on the barracks.
“Although this Government has delivered many high quality new
facilities already, there are still quite a few to look forward to over the
next 18 to 20 months,” he said.